Daya Terpasang, Daya Mampu, Daya Tersambung Dan Beban
Puncak Listrik PT. PLN(Persero) Wilayah XI Cab. Sumbawa Tahun 2014 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Bulan |
Daya Terpasang
(kwh) |
Daya Tersambung
(kwh) |
Daya Mampu (kwh) |
Beban Puncak (kwh) |
(1) |
(2) |
(3) |
(4) |
(5) |
1. Januari |
11,564 |
26.253.900 |
11,16 |
10,39 |
2. Pebruari |
11,564 |
26.492.950 |
11,16 |
10,05 |
3. M a r e t |
11,564 |
26.563.200 |
11,16 |
10,64 |
4. A p r i l |
11,564 |
26.837.700 |
10,91 |
11,05 |
5. M e i |
12,564 |
27.055.550 |
10,91 |
10,925 |
6. J u n i |
12,564 |
27.246.150 |
11,61 |
10,93 |
7. J u l i |
12,564 |
27.702.500 |
12,11 |
10 |
8. Agustus |
12,564 |
27.902.500 |
12,11 |
9,55 |
9. September |
12,564 |
28.055.150 |
12,11 |
10,2 |
10. Oktober |
12,564 |
28.420.450 |
12,15 |
10,523 |
11. Nopember |
12,564 |
28.622.300 |
12,15 |
10,6 |
12. Desember |
12,564 |
28.813.350 |
12,15 |
10,6 |
Sumber
: |
PT PLN (Persero) Wilayah NTB Cab.
Sumbawa PLTD Taliwang |
|
|
|
|
|
|
|
|